Reviews - Final Plat Inspection

Final Plat Plan Review

1. Show the percentage of grade for the new street. Streets must have less than 10% Grade.

2. The plans must include a copy of the water flow test results and duration chart. If you do not have a current water flow test, within the last 6 months, you will need to obtain the test from the Cherokee County Water and Sewer Authority or applicable City Water and Sewer Department. Cherokee County Water and Sewer Authority can be reached at 770-479-1813.

3. There must be a Fire hydrant installed within 200 feet of the subdivision.

4. Please add the following notes to the plans:

5. Schedule the Final Plat Inspection after all FMO comments have been addressed. The Final Plat will not be approved until the field inspection has been passed.